Martin Luther King, Jr. Park Improvements
City of Seattle
2200 Martin Luther King, Jr. Way S. Seattle, WA 98122
Scope of Work Performed:
- Installation and maintenance of temporary erosion and sedimentation controls
- Demolition of existing site elements
- Stripping and exporting sod
- Stockpiling topsoil for re-use on site
- Earthwork
- Concrete sitework including walls, stairs and paving
- Handrails on stairs
- Irrigation modifications
- New pedestrian and foundation accent light footings and associated paving
- Junction boxes and conduit connections